The contractor can submit a change order based on which of the following?

Study for the NCARB Continuum Education Exam. Gain insights with flashcards and multiple choice questions, each with detailed explanations. Boost your exam readiness!

Multiple Choice

The contractor can submit a change order based on which of the following?

Explanation:
Change orders are formal adjustments to a contract that handle changes in scope, price, or schedule. A delay directly affects the project’s finish date and, if it has financial implications or requires extending the timeline, it typically triggers a change order to authorize those time and cost adjustments. Shutting down is a suspension of work rather than a change in the scope or cost itself; weather is a condition that often leads to an extension of time rather than a change order, unless it also changes cost or scope. Start-up is simply a sequence activity, not a change to the contract terms. So the best basis for a change order among the options is delay, since it directly ties to ajusting the contract’s schedule and potential costs.

Change orders are formal adjustments to a contract that handle changes in scope, price, or schedule. A delay directly affects the project’s finish date and, if it has financial implications or requires extending the timeline, it typically triggers a change order to authorize those time and cost adjustments. Shutting down is a suspension of work rather than a change in the scope or cost itself; weather is a condition that often leads to an extension of time rather than a change order, unless it also changes cost or scope. Start-up is simply a sequence activity, not a change to the contract terms. So the best basis for a change order among the options is delay, since it directly ties to ajusting the contract’s schedule and potential costs.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy